How to carry out maintenance work with minimal traffic disruption

How do you keep infrastructure open to traffic while performing crucial maintenance work? The question is vital to ensure mobility in dense cities and avoid large road closure costs – both environmentally and economically.

The following article is written by one of COWI's leading specialists

Read more on COWI Insights

Owners and operators of urban infrastructure find themselves in a difficult situation. Urban populations are expanding rapidly, meaning much of our infrastructure is handling traffic far exceeding that envisaged at the time of design. This leads to increased rates of degradation and fatigue.

Furthermore, due to the impact of exhaust fumes on air quality, congestion has become a health and environmental issue, as well as an economic one. This makes it less acceptable to close highways or implement congestion-creating speed restrictions and lane closures. – even for vital maintenance work.

In other words; with urban road networks at maximum capacity, owners and operators need to find ways of keeping traffic flowing while they carry out maintenance work.

CLOSING THE UK’S MOST IMPORTANT BRIDGE WAS NOT AN OPTION

Let’s take a closer look at one such example.

Recently, Connect Pus, the operator of the Queen Elizabeth II (QE2) Bridge in London, UK, needed to carry out vital maintenance work on the bridge, which carries 80,000 vehicles a day.

Opened in 1991, the cable-stayed bridge carries the clockwise carriageway of London’s orbital highway, the M25, over the River Thames.

Due to age and fatigue, the bridge’s six movement joints needed to be replaced, requiring the removal of deck sections up to 4.5m long.

However, closing the UK’s most important bridge to carry out the work was not an option.

CHALLENGING THE INDUSTRY STANDARDS

The standard industry solution at the time – deploying steel plates over the joints – had a number of drawbacks: they restricted vehicles to 30mph, could not span double joints, did not cater for long span bridge movement and can block access from one side.

This option was clearly not going to meet the requirements for the QE2 Bridge.

A new solution was needed that did not require severe speed restrictions, could accommodate up to +/-350mm longitudinal movement and allowed work to be undertaken while traffic was flowing.

NEW SOLUTION KEPT TRAFFIC DISRUPTION TO A MINIMUM

In close collaboration with our client Connect Plus and contactor Jackson we developed an alternative solution: a temporary over-bridge system that allowed traffic to flow while the existing movement joint was removed from the underside of the bridge.

The temporary system (pictured below) comprised two sinusoidal asphalt approach inclines and a 5m long central steel bridging plate with integral movement joint. Light enough for easy fitting and removal, the modular units were installed over the existing joint during a single night closure.

Once the old joint was removed, the new permanent joint was installed during a single night closure, meaning disruption to traffic was kept to an absolute minimum.

500T OF CARBON AND MILLIONS OF POUNDS SAVED

By maintaining traffic flow and speed, the bespoke over-bridge system saved over 500t of carbon and millions of pounds in road closure costs. And, crucially, the repair work was invisible to motorists.

The system enables the replacement of movement joints while maintaining high-speed traffic flow (50 mph), and it is now used across the M25 and beyond.

In recognition of its game-changing impact, the project won Temporary Works Initiative of the Year at the 2015 British Construction Industry Awards.

Read more on COWI Insights

Jan. 11, 2019 Topics: Digitalisation
Digitalisation in the construction industry
The term BIM covers multiple concepts but in the end it's all about the process of digitalisation in the construction industry. BIM is an evolution and that takes time - it changes the ways we work in construction. Data and Information are central elements to the way the industry will achieve more efficiency and productivity through BIM. BIM should not become complex. BIM should be a technology-tool to make construction better. Want to learn more? Read the article here
Nov. 23, 2018
Highlights from InfraHub’s first conference
InfraHub's first conference was held on Thursday, 15th November. Its theme was 'Challenges and Benefits of Data Driven Asset Management.' The event attracted substantial interest and both speakers and participants contributed to an inspiring conference that focused on knowledge sharing and networking.
Sep. 12, 2018
New visual planning tool – 360° TBM
Bjarne Jørgensen, Executive Director for Asset Management at Sund & Bælt, tells about the visual tool and why it adds value to Asset Management Read more about the tool here
Sep. 11, 2018 Topics: Maintenance Rail
Sensors for railway maintenance
Flemming Saxtorph tells how Sund & Bælt apply new technology like sensors for railway maintenance. A field within infrastructure that is often characterized by a high level of complexity
Aug. 15, 2018 Topics: Technology Traffic
Flying with drone at Storebælt

Sund & Bælt is collaborating with COWI on drone flighting at the Storebælt Bridge with image recognition in relation to maintenance of the 325,000 tons anchor blocks.

Sign up for the newsletter